State Route 95 (Oak Ridge Turnpike) Improvements

The Tennessee Department of Transportation (TDOT) has roadway improvements proposed along SR 95 in three development phases. Phase One from the I-40 Gallaher Road interchange to the SR95/58 interchange was completed summer 2003.

Phase Two - SR 95/58 interchange to near Westover Drive

The improvements along this three-mile roadway section begin at the SR 95/58 interchange and extend to near Westover Drive.  From the SR 95/58 interchange to Southwood Lane, the improvements include widening from the existing two-lane roadway to a four-lane divided roadway with paved shoulders.  Just east of Southwood Lane, the roadway will taper to a five-lane section with paved shoulders and continue to Westover Drive.  In the area of Westover Drive, the roadway will taper back to the beginning of the Phase Three project where a four-lane divided roadway is being constructed.

The construction contract has been awarded to G.W. Wyatt and installation of erosion control measures and tree removal have been completed.  Grading and storm drainage is continuing.  Construction plans can be reviewed by appointment at the City Engineer's office, (865) 425-1807.  Construction is anticipated to be complete in May of 2012.

The State has revised roadway plans to better address the concerns of the Southwood Subdivision residents pertaining to safety and noise associated with the project.   Revisions to the plans along the subdivision include guardrail, drainage swales, protected vegetated areas, new tree plantings and shifting of the road alignment in some areas farther away from the homes. A 45 mph speed limit has been posted along the project.

 

Phase Three - Westover Drive to SR 62 (South Illinois Avenue)

THE PHASE THREE PROJECT IS CURRENTLY UNDER CONSTRUCTION - CONSTRUCTION SCHEDULING IS TENTATIVE AND IS SUBJECT TO CHANGE.

 

Last update to project – September 2009.

Press Release 5

The improvements along this 4.2-mile roadway section begin just west of Westover Drive and extend to SR 62. The improvements from Westover Drive to near Jefferson Avenue includes widening the existing four-lane non-divided roadway section to a four-lane divided roadway section with six feet shoulders to be designated as bike lanes, curb and gutter, and sidewalks. The improvements from Jefferson Avenue to SR 62 include widening to a five-lane roadway section with shoulders designated as bike lanes, curb and gutter and sidewalks.

 

The Tennessee Department of Transportation awarded the construction contract to Rogers Group, Inc. in March 2008. Work began on the project in early April 2008.

 

Work currently under construction includes concrete curbs, sidewalks and paving.

TDOT has granted a construction completion time extension to September 2010.

Main    Top


Sewer System Rehab Contracts

In 1992 the City began a program designed to reduce the amount of Inflow & Infiltration (I&I) entering the sanitary sewer collection system.  The reduction of I&I is important to eliminate occurrences of untreated wastewater bypassing the collection system.  This untreated water drains into the City’s stormwater collection system or, in the case of bypasses on the sewer interceptor line, directly into East Fork Poplar Creek.  Also reduction is important to reduce the cost of treating rainwater runoff that is retained in the collection system and deposited at the Wastewater Treatment Plant.  Normal dry weather flow at the plant is approximately five million gallons per day (MGD); however, during wet weather events flow can exceed 25 MGD.  Additionally, the City hopes to reduce the cost of damage claims from sewer backups. 

To date the City has let a total of 18 contracts as a result of the sewer rehab program.  Of those contracts 14 were for the direct purpose of reducing I/I. There were two contracts to clean and inspect lines using closed circuit television and two for the purpose of repairing or constructing sewer force main lines.  Approximately 211,248 feet or 19 percent of the 1,100,000 feet of city-owned sewer pipe has been rehabilitated.  Staff believes that it will be necessary to rehabilitate at least 25 percent of the system in order to significantly reduce the problems resulting from I&I.  Decreases in flow in individual collector lines serving neighborhoods where rehab has occurred have been observed.  Because of the City’s on-going voluntary commitment to reduce I&I the City has avoided a state mandated consent order. A consent order usually requires a much more aggressive and expensive program and frequently prohibits new connections to the collection system, which effectively eliminates new economic development.   In December of 2008, the Federal Environmental Protection Agency (EPA) contacted Public Works staff requesting information on sanitary sewer overflows (SSOs) and the City’s rehab program.  Subsequent conversations with EPA officials have lead staff to believe that it is likely the City will be required to implement a “Capacity, Management, Operation and Maintenance” (CMOM) program.  CMOM programs do not place restrictions on connections, but they do require additional engineering and capacity modeling, record keeping, mapping, etc. that will require funding for compliance.

Design and state approval for the next rehab contract, Contract “N,” is complete and the project was let for bid on July 23, 2009.  Notice to Proceed will be issued on December 7, 2009.  Contract “N” will include repairs in the southern portion of Mini-System E-11, along with repairs at all known point source problems City wide.  Construction is expected to be completed November 2010.

In March 2009, the City let for bid a contract (COR 09-05) to clean and inspect (TV) approximately 8,500 feet of sanitary sewer inceptor line running from Lafayette Drive west to near ORAU Way.  This project was completed in July 2009.  Information from the TV data will be used to determine repair needs on these segments of pipe.  These repairs, along with any new point source problems discovered after the time Contract “N” was let for bid will be combined to form the next rehab contract, which will be designated Contract “O.”  Bid letting for Contract “O” is anticipated in the winter of 2010.

Future Projects

At present, City crews are gathering information on repairs needed in mini-systems located in the Emory Valley area.  These repairs may be included in either Contract “O” or a future contract.

Main    Top


Rarity Ridge Infrastructure

Staff has received an EPA grant to supply City water to K-25 and Rarity Ridge.  EID was sent to EPA in October 2006 and a FONSI was issued in February 2008.  In September of 2008, the City sent the EPA a letter reconfirming it’s interest in and intent to continuing the application process.  In September 2009, a formal grant application was submitted and the EPA approved the grant in 2009.  LD&A is under contract for design work and construction is anticipated to begin in the spring of 2012.

Main    Top


 

Street Resurfacing

TDOT work began in June 2010 on portions of East Drive, Pennsylvania and Outer Drive.  Construction is expected to be complete by early August 2010.

City street resurfacing was let for bid and the contract was executed in June 2010.  Work is expected to be completed by October 2010.

Looking to use the new manhole leveling contractor.  Work to begin on December 7, 2010.

 Main    Top


Sidewalk Improvements - SRTS

Grant team setup and the first meeting was December 12, 2007.  Application to Council in February and submitted March 10.  Awards announced; recipients meeting in Nashville on January 7, 2009.  The State executed the contract in late December 2009.  The notice to proceed from the State received on February 28, 2010.  The City has completed environmental.  Cannon and Cannon near design completion.

 Main    Top


ETTP Roads

DOE planning to transition some roads on-site to the City.  Phase 1A approved by Council; implementing agreed upon items.  Phase 1A roads have been transferred to the City.

Main    Top